The project team will have to fix the defects in their work. 1 is incorrect because QC is based on inspection. The errors have already been identified so the project team must fix the errors. 3 is incorrect because peer review is an example of QC. The project team must fix the problems. 4 is incorrect because this statement is not applicable to the situation. Sorry – you don’t get to fire your project team members.