A RACI chart depicts the roles of each team member as Responsible, Accountable, Consult, and Inform. 2 is incorrect because a Pareto chart shows categories of failure and is used with quality control measures. 3 is incorrect because this term is not applicable. 4 is incorrect because this term is not applicable.