The project is not over. Rework must be done to bring the project back into alignment with the product requirements. 1 is incorrect. A change request is not the best answer for this question. Rework is required instead to correct the problem. A change request signifies an addition or subtraction from the project scope. 3 is incorrect because this is not a viable option. 4 is incorrect because the design document is not re-created. Rework is completed to meet the project objectives.