Once the changes have been approved, the project manager should reflect the additional time, cost, and scope changes accordingly in each baseline. 1 is incorrect. The changes are not reflected in the change control documentation because this documentation explains the process for how changes may enter the project scope. 2 is incorrect. A risk assessment of each change is completed as part of the change control process—not after the change has been approved. 3 is also incorrect. The change control system is not updated because of the change.