When Holly uses a previous project’s WBS to create the current project’s WBS she is using a template. 1 is incorrect because she is not estimating at this point in the project. 2 is incorrect because while this may be a loose example of historical information, WBS template answers the question more accurately. 3 is incorrect because this is not an example of poor project management.