The scope management plan explains how the project scope will be managed and how scope changes will be factored into the project plan. 1 is incorrect because the change control system (CCS) is the process of how changes are presented, processed, documented, and managed. 2 is incorrect because the cost management plan dictates how cost variances will be managed. 4 is incorrect because the risk management plan details how risks are planned for and responded to.