The project manager needs to revise the project management plan and project documents to reflect the changes. If the changes have already been implemented , this means the change had already been analyzed, its impact evaluated, and then approved by the change control board. The only things that's left to do is to update and revise the documents. You need to follow the proper flow and sequence for getting changes implemented to answer change related questions.