This question can be tricky as it doesn't clearly state whether or not the Project Manager received a formal communication of the delay from the vendor. Since a Project Manager should proactively look for any event that may delay the project schedule, Option C is the best alternative. Option B is harsh, especially in a situation that is beyond the vendor's control (e.g. political unrest in the country).