The repair must be reviewed for accuracy. 1 is incorrect because the repair must be correct before the project can move forward. If the repair is assumed to be correct then the review of the time delay may be inaccurate because of future rework, waste, or a series of failures because of the inaccurate rework. 2 is incorrect because the repair must be reviewed for accuracy first. 3 is incorrect because this is not the most pressing issue at this point in the project.