The team comprised of 5 people originally, however note that the project manager was also a part of the overall team apart from your team members, so in total there were 6 people originally. Now 2 more people have been added, which brings the total to 8 people. Formula = [N(N-1)/2] Formula = [8(8-1)/2] =28