Because the SOW provides all these elements. 1 is incorrect because the proposal does not provide these elements, but focusing on how the solution can be implemented. 2 is incorrect because the RFP asks the vendor to provide a proposal. 3 is incorrect because this document comes from the vendor to the buyer and is focused on price only.