The project with a CPI of .89 is not doing too well. For every dollar the project spends it loses eleven cents. 1 is incorrect. The project is not performing well. 3 is incorrect. The project will likely finish over budget. 4 is incorrect. The probably won’t be in alignment with the cost baseline.