Someone who doesn't want to take risks is called risk averse and the Project Manager seems to be part of such an organization. Option C risk neutral describes a person/or an organization which is indifferent to the risk, and Option A risk seeker suggests an aptitude to take risks with an opportunity for higher returns. Option D risk mitigation is a risk response strategy and is an invalid choice.