The resource calendar controls when resources, such as project team members, consultants, and SMEs are available to work on the project. It takes into account vacations, other commitments within the organization, restrictions on contracted work, overtime issues, and so on. 1 is incorrect because the project calendar details when work is allowed on the project. 3 and 4 are incorrect because neither is a valid answer.