A change request form will allow the change request to be documented, considered, and approved or declined. 1 is incorrect. This is not a correct statement about the circumstance described. 2 is incorrect. This is incorrect; scope statements can be changed if the need is appropriate. 4 is incorrect. The project sponsor is not the party to talk to about changes at this point. A change request is the best form of action.