Schedule compression technique is useful not only during project planning to see if the desired completion date can be met, but also during integrated change control to look at the schedule impacts of changes to time, cost, scope, or risk. Option B seems to be in good faith but doesn't address the immediate problem. Option C should be done once all the alternatives are explored to minimize the adverse effect of the change on the project schedule and other constraints.