Because a should-cost estimate, also known as an independent estimate, is prepared in-house or by a third party. This estimate then measures all other estimates against it. 1 is incorrect because this defines the mid-stage estimate for the entire project. 2 is incorrect because this is the most-detailed estimate based on the WBS for the entire project. 3 is incorrect because this is not a valid term.