The total funds required in the project are those included in cost baseline, plus management reserve if any. Remember, the cost baseline includes contingency reserves because the cost baseline will include projected expenditures plus anticipated liabilities. Please refer to PMBOK® Guide - Fifth Edition Project Cost Management PN 206 for more details.