This is an example of direct costs because the training is needed to complete the current project’s work. 2 is incorrect since indirect costs are shared across multiple projects. 3 is incorrect. This is not an example of a variable cost. Variable costs fluctuate depending on the conditions within a project. 4 is incorrect because fixed costs are persistent throughout the project—such as leasing a piece of equipment.