The WBS is the scope baseline; technically the WBS, the WBS dictionary, and the detailed project scope are the scope baseline. 1 is incorrect because the time and cost baselines do not reflect the scope. 3 is incorrect because the project charter does not capture all the deliverables the project will create. 4 is incorrect because the project scope is decomposed into the WBS. The WBS, in effect, reflects the entire project scope.