Administrative closure does include analyzing project success and failure. 1 is incorrect because scope verification verifies the project deliverables. 3 is incorrect because lessons learned is part of administrative closure – which answers this question more completely. 4 is incorrect because there’s no evidence that a contract was even used in this project. In addition, choice 1 answers the question.