The Project Manager is in the process develop schedule. Since the project schedule has already been approved, it implies Option A, B, and D are already completed as part of the processes estimate activity resources, develop schedule, and sequence activities. The next step would be to treat this estimate as a schedule baseline and start tracking the project as part of the process control schedule.