The inaccurate values provided by the team members can negatively influence the project's performance statistics. It is the primary responsibility of the project manager to first provide information that is truthful and accurate. This should be followed by a meeting with the team regarding the impact of their actions and if that does not solve the problem , their actions should be reported to their functional managers.