The scope change control system documents how changes are authorized for a project. 1 is incorrect. Not every project will have a change control board. In addition, the processes for change are documented in the scope change control system. 2 is incorrect. This is not a valid answer for this question. 4 is incorrect. The charter authorizes the project; it does not document the change control process.