Items at the top of the Product Backlog should be small enough to fit in one Sprint. They should also be clear and detailed enough but not too detailed (eg with all the tasks identified), as it would be an upfront planning. Tasks are created
gradually during the Sprint. The Scrum Guide doesn't recognize a 'definition of ready' concept.