The most important thing to calculate is the completion date of the project. That's also the most important thing that should be communicated with the customer. Traditional criterial such as lines of code or man-hours spent on the project
are not good measures of performance. The velocity can be a guide in forecasting the completion date, but is not enough, and is not a main reporting item.