Concept:The total work done is directly proportional to the number of workers, the number of days, and the hours worked per day.
Explanation:Let
y be the number of additional persons needed.
From the first part: 480 persons work 10 hours/day for 10 days to complete
41 of the work.
So,
M1=480,
D1=10,
H1=10,
W1=41.
The remaining work is
1−41=43.
This remaining work must be done in 20 days with 8 hours/day.
So,
M2=480+y,
D2=20,
H2=8,
W2=43.
Use the work equivalence formula:
W1M1×D1×H1=W2M2×D2×H2.
Substitute the values:
41480×10×10=43(480+y)×20×8.
Simplify each side. Left:
4148000=48000×4=192000.
Right:
43(480+y)×160=(480+y)×160×34=(480+y)×3640.
Thus,
192000=(480+y)×3640.
Multiply both sides by 3:
576000=(480+y)×640.
Divide by 640:
900=480+y.
So,
y=900−480=420.
Answer:420 additional persons are required.