ICSE Class 10 Physics 2017 Solved Paper

Show Para  Hide Para 
A pulley system with VR=4 is used to lift a load of 175kgf through a vertical height of 15m. The effort required is 50kgf in the downward direction. (g=10Nkg1)
Calculate:
© examsnet.com
Question : 29
Total: 65
Work done by the effort.
Solution:  
Work done be the effort = Effort ×dE
Given : Effort =50kgf =50×10=500N
WE=E×dE=500×60J
=30,000J
© examsnet.com
Go to Question: