The management contingency reserve is an amount of funds set aside for unplanned events that consume the project budget. 1 is incorrect because while unknowns may be risks this is not the best response. 2 is incorrect because it does not answer the question as completely as 3. 4 is incorrect because the project has not failed at this point.