A project with a CPI of .98 has to spend one dollar for every 98 cents worth of work it receives. 1 is incorrect. There is no evidence the project is late. 2 is incorrect. The project is actually losing money with this CPI, not making it. 4 is incorrect. A CPI of .98 does not mean the project is 98 percent complete.