The project is done. 2 is incorrect because regardless of the team’s status the project has been completed. 3 is incorrect because there’s no need to do a change request – the project is completed. 4 is incorrect because your project is done. It’s up to the project manager of the installation project to request for additional labor if he feels it’s needed.