Correct Answer is D. In the PERT calculation, the standard deviation is calculated by squaring the standard deviation for each of the activities on the critical path of the project, adding them together and then taking the square root. This is the standard deviation of the project. Plus or minus two standard deviations from the expected value of the project duration will have a range of values such that the project has a 95% probability of actually finishing within the dates calculated.