A Risk Breakdown Structure illustrates the risk categories within a project. 1 is incorrect; the WBS shows the decomposition of the project scope. 2 is incorrect because the OBS shows the structure of an organization, not the risks within the organization. 4 is incorrect because the BOM describes the materials needed in order to build the project scope.