The total duration of this project is 26 days. The path ACFGJL will last for 24 days, allowing two days of float among the noncritical activities. If Activity G increases in duration by two days the duration of the path will be 26 days, meaning there is no additional float allowed for Activity J. The other choices are incorrect calculations of the question.