Risk identification is an iterative process. The project team must proactively look for risks. 1 is incorrect because risk doesn’t happen only early in the project, but throughout the project. 2 is incorrect because risk identification doesn’t happen in initiation, but iteratively throughout the project. 4 is incorrect because risk identification happens sans schedule, as needed.