Five jobs (J1, J2, J3, J4 and J5) need to be processed in a factory. Each job can be assigned toany of the five different machines (M1, M2, M3, M4 and M5). The time durations taken (inminutes) by the machines for each of the jobs, are given in the table. However, each job isassigned to a specific machine in such a way that the total processing time is minimum. Thetotal processing time is __________ minutes.
M1 | M2 | M3 | M4 | M5 | |
---|---|---|---|---|---|
J1 | 40 | 30 | 50 | 50 | 58 |
J2 | 26 | 38 | 60 | 26 | 38 |
J3 | 40 | 34 | 28 | 24 | 30 |
J4 | 28 | 40 | 40 | 32 | 48 |
J5 | 28 | 32 | 38 | 22 | 44 |