Question : 59
Total: 65
A project consists of six activities. The immediate predecessor of each activity and the estimated duration is also provided in the table below:
If all activities other than S take the estimated amount of time, the maximum duration (in weeks) of the activity S without delaying the completion of the project is ___________
Activity | Immediate predecessor | Estimated duration (weeks) |
---|---|---|
P | - | 5 |
Q | - | 1 |
R | Q | 2 |
S | P,R | 4 |
T | P | 6 |
U | S,T | 3 |
- Your Answer: