Given: Number of days taken by 45 men to dig a pond = 25 days Concept used: Total work = Number of men × Time taken Calculation: Total work = (45 × 25) units Number of men required to dig it in 15 days =(45×25)/15 men ⇒ 75 men ∴ The number of men to be employed is 75