An agile project and non-agile project both have the same general goal, but the detail level in an agile project is different. The agile project has less detail than a non-agile project because agile methods typically involve technology
or requirements that can not easily be defined in the agile project charter. An agile charter is subject to change as the project progresses – it is a living document. The other responses are incorrect because they are not true statements
regarding agile project charters.