The correct answer is that agile projects have a fixed cost and time, but the scope can vary. The other responses are incorrect because they don’t accurately define the agile triangle of constraints. Agile projects have a scope that’s
flexible, but attempt to have a fixed cost and time. A company knows the amount of money they plan to spend over a certain timeframe, but the actual work done in that time will only be determined….over time.