4 is correct because transparency is focused on the full team having visibility and agreement regarding work within a sprint. 1, 2, and 3 are incorrect. 1 is incorrect because although the description is correct, visibility is not the
appropriate term for the Scrum pillar. 2 and 3 are incorrect because inspection and adaptation are not the focus of the definition of done, which is more about openly setting expectations.