1 is correct because sprint retrospectives are performed to determine areas of improvement and to allow the team to make those adjustments in the future. 2, 3, and 4 are incorrect. 2 is incorrect because the retrospective could be during
an iteration or release. 3 and 4 are incorrect choices because Sarah does not need to have a demonstration at the beginning of each cycle focused on developers.