The correct answer is that each project cycle has a fixed time and fixed cost, but the scope of work completed within each cycle could vary. A model that represents fixed cost and fixed time, but has a variable scope, is an agile triangle
of constraints. The other responses are incorrect because a fixed scope represents the established model of the triangle of constraints; fixed time, fixed scope, and fixed cost do not accurately portray the agile triangle of constraints.