The correct answer is to have the product owner and the delivery team prioritize the backlog. This is done to ensure the alignment with stakeholder priorities. The product owner should be well-versed in business priorities and customer
needs. The other responses are incorrect because prioritization is done just in time for each iteration; it’s not charter based; the entire stakeholder team doesn’t prioritize nor does it use Planning Poker.