The team is behind in scope compared to projections is the correct response. When a line shows scope built at a very low level compared to projected progress, the indication is that the story points completed are not where they were forecasted
to be. The other responses are incorrect. We don’t know what the projected spending is because the chart gives no indication of anything related to spending; it does show that there’s an issue with scope, so the team is not fine.