The correct answer is that EVM can’t tell Hunter, or the team, that what they are providing is valuable to the project. The other responses are incorrect because EVM can indeed be used to track the performance of a project if the baseline
hasn’t changed; EVM is able to adequately track if the project is on time and budget; while EVM can’t calculate the business value of the project, it can show if the project is on budget or not.