The product owner should share the updated backlog items to make sure the entire team understands how to move forward. The other responses are incorrect. The project scope is based on the prioritized requirements; to uncover any obstacles,
accomplishment and roadblock questions are answered during Daily Scrums; a project’s success is not discussed in a sprint planning meeting.