A velocity chart measures the team’s work capacity per iteration. After tracking several iterations by using the team’s average velocity of previous iterations, the velocity chart becomes a powerful tool for planning and estimating. An
added benefit of the velocity chart is that it considers interruptions and scope creep. The other responses are incorrect because velocity charts don’t show these items. Other matrices may be used to track members, time, and the number
of hours used to date.