The agile team creates and owns the story point sizing process. They are the most qualified to determine the amount of effort needed to complete each story. The other responses are incorrect. The PMO and business partner do not have that
level of detail involved in the project. While the agile team leader supports the team in creating the story point sizing, they are not responsible for the task itself.