The correct answer is the assurance that one responsible party is accountable. More than one party should be accountable. This is untrue in agile projects; the team is accountable, and Manuel needs to bring this issue to the team. The
other responses are incorrect: They are all accurate descriptions of options used to handle issues in an agile project; Manuel should take his problem to the team to allow for better decisions using multi-functional knowledge; to build
team relationships; to ensure that the group takes ownership of the problem, not Manuel personally.